| Purpose Of Use | Office and Dormitory Buildings |
| Building Model | Lightweight Steel Panel Prefabricated Structure |
| Number Of Buildings | Block 7 |
| Total Area | 2.120 m² |
| Project Year | 2026 |
| Region To Be Used | Ankara / Turkey |
| Completion Time | 22 Days |
We constructed prefabricated construction site structures for the highway project located between Ankara and Kırşehir. The prefabricated mobilization units we installed as part of the project were built at two separate locations in Ankara and Kırıkkale.
We delivered our 2,120-square-meter construction site mobilization structures in just 22 days. With our construction site structures, which will be used in the improvement and renovation of the Ankara–Kaman (Kırşehir) highway, we are contributing to the renovation of roads and the shortening of distances.
With our construction site offices at two locations, we have created pleasant working environments for the project’s technical team. Through our dormitory buildings, we provide project field workers with the comfort of home. Our dining hall buildings offer a spacious and hygienic environment, providing an extra opportunity for relaxation alongside delicious meals. With their structural safety, ergonomics, and comfort, our prefabricated structures make an additional contribution to increasing construction site efficiency.
As Karmod, we reflect our expertise in construction site mobilization through project-specific flexible solutions. The geographical structure and climatic characteristics of the region where the mobilization will be set up are fundamental factors considered before the construction project begins. The purpose and duration of the structures’ use are other key considerations. The nature of construction sites in highway and renewable energy sectors, which require relocation at specific intervals, is also part of these evaluations.
Based on this information, which is brought to the table at Karmod’s technical office even during the project phase, a study is conducted. At this stage, the building model and technical details are determined and shared transparently with the client. The primary objective here is to present the most suitable and efficient mobilization solution for the project where the structures will be used. For example, the building and wall structure models, as well as insulation material selection, are determined based on the climate characteristics of the region where the mobilization will be deployed. With its expertise in this field, Karmod develops building solutions that benefit project investors at every stage. It guides investors toward the right solutions for dormitory and dining hall structures, office buildings, and local and healthcare facility buildings. A lightweight steel panel system was used in the buildings within the project scope.
For the Ankara–Kaman (Kırşehir) highway project, our teams simultaneously carried out mobilization setups at two separate locations. The on-site installation of the structures, consisting of 7 blocks, was completed in 22 days and delivered for project use. Our building complex, totaling 2,120 square meters, included office, dining hall, dormitory, and community buildings.
K-CNS- MN10072697 / BN: 00009520
From one end of the world to the other, we enable our customers to reach the ready-made construction sector produced with the new technology of the world. We guarantee reliability through technology and innovation, flexible commercial models and smart supply chain solutions that add value for you, following the project production network.
Discover